Subic Bay Freeport – The Subic Bay Metropolitan Authority (SBMA) is eyeing the completion of big-ticket projects under President Ferdinand Marcos Jr.’s administration.
Speaking before stakeholders at the Build Better More Infrastructure Forum held at the New Clark City (NCC), in Capas, Tarlac, SBMA Chairman and Administrator Eduardo Jose L. Aliño said that the agency aims to complete these infrastructure projects by 2028.
Environmentally friendly and cost efficient service
“On top of our list is our initiative to become the first Philippine port equipped with shore power connection for ships. By 2028, we look to complete the project and deploy the shore power facility that looks to reduce the air pollution from ships by 95%. The project cost is around P250 million.”
The Shore Power Connection for Carbon Neutral Ports project will start construction at the New Container Terminal in 2025 for Phase 1, and at the Naval Supply Depot (NSD) and Ship Repair Facility (SRF) from 2026-2027 for Phase 2.
“This will provide shoreside electrical power to a ship at berth while its main and auxiliary engines are shut down. Shore power cuts air pollution from ships at berth by 95 percent,” he said.
The project cost will be under the General Appropriations Act (GAA) of the National Government for 2025, which will be around P100-million for Phase 1 and P150-million for Phase 2.
Logistics facility for trucks
“To ensure that the growth in cargo will not lead to road congestion, we are now in the process of constructing a state-of-the-art truck holding area in our Tipo area. The project will include automated gates, optical plate scanners and amenities for truck drivers and clients. The project will cost around P100 million and will be completed by 2028,” Aliño said.
The Logistics Facility for Trucking Services will provide a holding area that can accommodate 100 trucks and vehicles. The construction of parking areas with amenities for cargo trucks and trailers will also be undertaken.